LegislationOriginal
Fast track and PINM: where France's AI data center projects stand
Twenty-one months after the Paris AI Action Summit, Campus IA in Fouju is the only announced AI project with a signed fast-track grid connection. Fluidstack has withdrawn its €10bn pledge, and a court has suspended Sesterce's building permit in the Drôme. We found no decree qualifying a data center as a "projet d'intérêt national majeur" (PINM).
On 9 February 2025, the Élysée announced €109 billion of private investment pledges in AI, a large share of it for data centers (info.gouv.fr). In late January 2026, after a review meeting at the Ministry of the Economy, Le Monde Informatique reported that none of the announced AI data centers had been connected to the grid yet (Le Monde Informatique).
This tracker follows each announced project using public sources. It will be updated as projects move.
The framework: fast track and PINM
Two tools were meant to shorten timelines: a faster grid connection procedure run by RTE, and a planning status, PINM, opened to data centers in May 2026.
Fast track grid connections
The energy regulator CRE approved RTE's "fast track" procedure on 7 May 2025 (CRE). It covers very large consumers, from 400 MW to 1 GW, connected to the 400 kV grid on sites the State has identified in advance, with connections expected around 2028-2029.
Four sites were named at Choose France in May 2025: Fouju and Montereau in Seine-et-Marne, Escaudain in the Nord and Le Bosquel in the Somme. A fifth, at the Grand Port Maritime de Dunkerque, was added in December 2025 (RTE). RTE has since listed Poulainville (Somme) in July 2026, and Loon-Plage (Nord) and Bure/Saudron (Meuse) in September 2026 (RTE services).
Campus IA and RTE signed the first fast-track agreement on 26 January 2026, for the Fouju site. It provides 240 MW by end-2027 and 700 MW before end-2029, with room to grow to 1,400 MW (RTE).
PINM status
Law no. 2026-403 on simplifying economic life was promulgated on 26 May 2026 and published in the Journal officiel the next day (vie-publique.fr). Its article 35 allows a data center to be qualified as PINM by decree. Five days before promulgation, the Constitutional Council struck down 25 articles as unrelated to the original bill, without censuring any provision on substance (vie-publique.fr).
The status has limits for data centers. It does not give them the early, decree-based recognition of "overriding public interest" used to derogate from protected-species rules (Gossement Avocats). The same article also lets the authorities refuse a building permit where water resources are under structural stress (Kohen Avocats).
Each qualification needs its own decree, and we found none published for a data center as of 24 November 2026. In May 2026, the government told the Senate that Campus IA had not applied for the status (Sénat).
Grid demand: the published figures
Demand for grid capacity has grown much faster than signed commitments. The original plan, set out in February 2025, expected 16 sites to be operational in 2025, 7 more in 2027 and 12 in 2028 (Le Monde Informatique).
| Date | Figure | Source |
|---|---|---|
| May 2026 | RTE had reserved about 18 GW for about 80 data center projects; most request 100 to 200 MW, about ten exceed 400 MW | TechPi |
| May 2026 | 76 connection requests (16 GW), against about 40 projects (5 GW) at end-2024; about 10% have taken a final investment decision and signed a works agreement | AEF info |
| 2026 | Data centers connected over the past two to three years use on average 20% of the power they requested | Les Énergies Renouvelables |
| 2026 | Eight existing data centers are connected directly to RTE's high and extra-high voltage grid, about 800 MW in total | TechPi |
| 10 Feb 2026 | About 75% of project holders have secured a site or are close to it; 52 companies receive State support | Le Monde Informatique |
| 30 Jan 2026 | 63 suitable sites identified, 26 secured by a project holder, 5 fast track; 28.6 GW sought, of which 5.8 GW under connection commitments | Ministère de l'Économie, L'Usine Nouvelle |
Project by project
Of the ten projects tracked below, two have work under way on site, one is suspended by a court and one has been withdrawn. The rest are at the announcement or site stage, based on public information.
| Project | Site | February 2025 pledge | Status | Latest public milestone |
|---|---|---|---|---|
| Campus IA (MGX, Bpifrance, Mistral AI, Nvidia) | Fouju (77) | 1 GW AI campus, up to €50bn from MGX (The Media Leader) | Under construction | Fast-track agreement signed 26 Jan 2026. Building permit issued 28 Aug 2026 (FNE Île-de-France); first works began late August (Mesinfos). Developer schedule: first building in operation 2027-2028, last in 2038 (environmental filing) |
| Data4 Escaudain (Brookfield) | Escaudain (59) | €20bn from Brookfield, of which €15bn for data centers via Data4 | Site secured | Launch confirmed 12 Jun 2026: 700 MW on 33 ha, €5bn. Fast-track site |
| Data4 Cambrai (Brookfield) | Cambrai (59) | Part of the same pledge; site set to host 1 GW (DCD) | Announced | DCD reported that work could begin in 2026. No public construction start found |
| Fluidstack AI supercomputer | Le Bosquel (80) | €10bn, 1 GW, phase 1 to be operational in 2026 (Business Wire) | Withdrawn | Withdrawal reported by Bloomberg in March 2026. Site awarded in June 2026 to a SoftBank-Sesterce joint venture (1 GW) (StorageNewsletter) |
| Mistral AI cluster at Eclairion | Bruyères-le-Châtel (91) | Largest AI cluster in Europe, amount not specified | Fluidstack also left this project (The Energy Mag). Mistral raised $830m in debt in March 2026 for 13,800 Nvidia GB300 GPUs and 44 MW (DCD) | |
| OpCore (Iliad, InfraVia) with EDF | Montereau (77) | Over €3bn from Iliad | Announced | Exclusive negotiations with EDF announced Nov 2025, €4bn. Fast-track site; first commissioning expected in 2027 (EDF) |
| Evroc | Mougins (06) | Up to €4bn, 96 MW, construction expected to finish in 2025 | Announced | No public update on construction found; listed as planned by Datacentermap |
| Sesterce compute center | Alixan, Rovaltain (26) | €400m | Suspended | Permit issued 18 Dec 2025 for 40 MW, extendable to 80 MW. Suspended on 10 Jul 2026 by the Grenoble administrative court pending a ruling on the merits (court order); Sesterce has appealed (AFP / Connaissance des Énergies) |
| Digital Realty | Paris region, Marseille | Over €5bn, 13 new data centers | Under construction | Work on MRS5 in Marseille (€300m) announced as started in May 2025 (DCD); ground broken on a new Paris site in May 2026 (DCD) |
| Prologis | Île-de-France | €3.5bn, 400 MW | Announced | At Choose France 2025: €6.4bn including four data center projects, reported at 584 MW (DCD). No later update found |
February 2025 pledges from The Media Leader unless stated. Not yet tracked: Amazon (€6bn, including €1.2bn announced earlier), Apollo (€5bn, energy) and Telehouse (€400m).
Announcements since the summit
Most of the pledges added since February 2025 are in Hauts-de-France.
On 1 June 2026, SoftBank announced up to €75bn for 5 GW of AI data center capacity in France. Its first phase, worth €45bn, targets 3.1 GW in Hauts-de-France before the end of 2031, on sites in Dunkirk (Loon-Plage), Le Bosquel and Bouchain (Yahoo Finance / Quartz). EDF is a partner for Bouchain, and Schneider Electric for an industrial hub at the port of Dunkirk (Euronews).
The same month, Brookfield raised its pledge from €20bn to €30bn (DCD). The Campus IA consortium announced a second site, still to be selected, with a national target of up to 3 GW (Abu Dhabi Media Office).
The June 2026 edition of Choose France totalled €93bn of foreign investment commitments (Euronews). The domestic edition, held on 23 November 2026, listed 273 projects worth €42.5bn, 40 of them in digital (TechPi).
Outside France
Grid access is also the main constraint cited in the United States, the United Kingdom and at EU level.
In the United States, Epoch AI estimated in April 2026 that Stargate, OpenAI's $500bn program, had about 0.3 GW operational in Abilene, Texas, with six other US sites under construction (Epoch AI). At least three of the seven sites plan on-site gas generation to avoid grid queues (Epoch AI).
The UK government calls timely grid connection the single biggest blocker for its AI Growth Zones (GOV.UK). In September 2026, reports said Nscale's site in Loughton, Essex, may have to wait until the 2030s for enough power, and Scotland halted approvals for new hyperscale AI data centers (Euronews). Microsoft has withdrawn from the Essex project with Nscale (City AM).
At EU level, InvestAI was announced at the same Paris summit, with €20bn for AI gigafactories (European Commission). The call for tenders opened on 30 July 2026 for up to seven gigafactories, with up to €10bn of EU and national funding expected to unlock at least €20bn of private investment (European Commission). It closed on 12 November 2026 (Digital Skills & Jobs Platform).
How this tracker works
Statuses reflect public sources available on 24 November 2026: company releases, RTE and CRE documents, court decisions, official filings and press reports. A project marked "no public update found" may still be moving forward. Operators can send corrections or additions to the editorial team, and each change will be dated and sourced.
Main sources: Le Monde Informatique (Jan 2026) · Le Monde Informatique (Feb 2026) · CRE, fast track approval · RTE, fast-track sites · Ministère de l'Économie, 30 Jan 2026 · Vie-publique, law of 26 May 2026